Chagrin Falls, Ohio · Commercial pool

Project complete · 2026

Lake in the Woods Pool Renovation

Completed: a 4,300-square-foot commercial pool renovation in Chagrin Falls, Ohio, delivered in 12 working days. The scope included membrane tear-out and replacement, plus 220 linear feet of tile-band removal and reinforced concrete repair.
FacilityCommercial pool
Project size4,300 sq. ft.
Onsite schedule12 working days
Installed systemReinforced PVC membrane
Before
Lake in the Woods Pool Renovation before renovation
Existing condition
After
Lake in the Woods Pool Renovation after PVC membrane installation
Completed system

The existing condition

What the crew walked into.

The existing PVC membrane needed replacement, with deteriorated concrete and a tile band requiring removal and repair before the new interior could be installed.

Field execution

How the system was rebuilt.

Ferguson Aquatics removed and disposed of the previous membrane, completed 220 linear feet of tile-band removal and reinforced concrete repair, prepared the shell and installed the new reinforced PVC membrane. Black racing lanes, wall targets, a break stripe and depth markers complete the finished pool.

Documented execution

From tear-out to a finished aquatic system.

Each phase is shown in sequence so facility teams can see the preparation and detailing behind the completed surface.

Lake in the Woods pool before renovation
01

Existing pool

The pool before draining and removal of the previous membrane.

Exposed Lake in the Woods pool shell after membrane removal
02

Membrane tear-out

The previous membrane was removed to expose the shell for repairs and preparation.

Completed Lake in the Woods membrane installation before filling
03

New interior installed

The blue membrane interior, racing lanes and wall targets before filling.

Completed Lake in the Woods pool with blue membrane and black racing lanes
04

Completed pool

The finished renovation with water in the pool after 12 working days.

Scope of work

Detailed for long-term performance.

Each item was coordinated as part of the same waterproofing assembly—not treated as a separate finish detail.

  1. 01Removal and disposal of the previous PVC membrane
  2. 02220 linear feet of tile-band removal and reinforced concrete repair
  3. 03Shell preparation for the replacement membrane
  4. 04Installation of the new reinforced PVC membrane interior
  5. 05Black racing lanes, wall targets, break stripe and depth markers