Existing pool
The pool before draining and removal of the previous membrane.
Chagrin Falls, Ohio · Commercial pool
Project complete · 2026


The existing condition
The existing PVC membrane needed replacement, with deteriorated concrete and a tile band requiring removal and repair before the new interior could be installed.
Field execution
Ferguson Aquatics removed and disposed of the previous membrane, completed 220 linear feet of tile-band removal and reinforced concrete repair, prepared the shell and installed the new reinforced PVC membrane. Black racing lanes, wall targets, a break stripe and depth markers complete the finished pool.
Documented execution
Each phase is shown in sequence so facility teams can see the preparation and detailing behind the completed surface.

The pool before draining and removal of the previous membrane.

The previous membrane was removed to expose the shell for repairs and preparation.

The blue membrane interior, racing lanes and wall targets before filling.

The finished renovation with water in the pool after 12 working days.
Scope of work
Each item was coordinated as part of the same waterproofing assembly—not treated as a separate finish detail.
Photo documentation
Images are shown without aggressive cropping so the shell geometry, transitions and completed work stay visible.









Specified material