Before draining
The existing pool before membrane tear-out began.
Chagrin Falls, Ohio · Commercial pool
In progress · Updated October 8, 2026


The existing condition
Removing the previous PVC membrane revealed existing shell issues that need to be repaired before the new interior is installed. The photos below document the filled pool, the drained pool with its old membrane still in place, and the exposed shell after tear-out.
Field execution
Our crew completed removal and disposal of the previous membrane and began removing loose concrete and tiles. Next comes shell repair and surface preparation before the new membrane installation. This page will follow the project as work continues.
Documented execution
Completed stages shown in order. Repairs and installation will follow.

The existing pool before membrane tear-out began.

Water removed, with the previous PVC membrane still in place.

Previous membrane removed and disposed of. Loose concrete and tile removal has begun.
Scope of work
Completed work and upcoming stages for this active renovation.
Photo documentation
Images are shown without aggressive cropping so the shell geometry, transitions and completed work stay visible.






Next stage
More progress photos will be added as the renovation continues.